Posted on: June 5, 2018

Night work on 2nd and 3rd Streets South project begins tonight

Downtown-Map---nighttime-detours (060518)

The city of Nampa will begin night work on 2nd Street South which will be closed to traffic from 7 p.m. to 7 a.m. tonight. Traffic will be detoured (Detour 1 on the map) via 16th Avenue South (SH-45) to 7th Street South to 12th Avenue South.

Crews are paving 3rd Street South today and will shift traffic to the newly paved north side of the street tomorrow. The contractor will then begin night work Wednesday to excavate the south side of 3rd Street South. Night work will continue through Friday. Traffic on 3rd Street South (Detour 2 on the map) will be detoured via 12th Avenue South to 7th Street South to 16th Avenue South.

Downtown-Map---nighttime-detours (060518)

The rebuild is needed to improve the severely deteriorated pavement. Sidewalk corners will also be improved to fit Downtown Historic Streetscape Standards and to comply with the Americans with Disabilities Act (ADA). Several underground utilities are also being upgraded.

The $2.8 million project is scheduled to be complete in late August. The contractor is Idaho Materials and Construction of Nampa.

The city will continue to provide updates about the project at http://www.cityofnampa.us/projects/downtown. If you have questions, please call 208-465-2221 or email projects@cityofnampa.us.

Additional Info...
Facebook Twitter Google Plus Email

Other News in City of Nampa

Pooch Party 2018_eflyer

11th Annual Pooch Party Stroll & Splash

Posted on: August 16, 2018
City of Nampa

Mayor Kling expresses condolences

Posted on: June 11, 2018
Spring Kickoff 2018_eflyer

Nampa Rec Center’s Spring Kickoff

Posted on: April 13, 2018
Brush Up Nampa 2017

Brush-Up Nampa seeks participants

Posted on: March 13, 2018
Nampa Proud _Black and Med Blue.jpg

City of Nampa Snow Update

Posted on: February 26, 2018
Mayor Bob Henry

A statement from Mayor Bob Henry

Posted on: November 8, 2017